Nissan Motor Company Project

04 Feb 2014 4:40 AM | Anonymous

CEA Project Logistics recently executed a project for the Nissan Motor Company which involved the transportation of factory parts which totaled 5,200 tons.

The factory parts arrived by ship at Laem Chabang Port and were unloaded by the vessel onto the dock below. Two CEA 50 ton cranes were then used to lift the parts on to three different types of trailer Flatbed, Lowbed and Multi Axle, this was due to the cargo being oversized and varying in weight. All cargo was secured with ratchet straps and transported to the CEA yard in Laem Chabang for two weeks storage until delivery date.

Upon delivery date the same configuration of trailers made the 82km journey to the Nissan facility in Samut Prakan. As these parts were oversized cargo CEA employed the services of the local Highway Police for a full escort to ensure the safety of all road users.

 

 

 

 

 

 