TGI handled a full dismantling and plant relocation from Cobar NSW to San Juan Argentina. This was great job, it took 8 months to complete from dismantling to arrival at San Juan. The highlight of the job was the 90 tonne Mill Shell Transport from site to Newcastle port which was around 800 km.

The route was carefully planned by our team and our transport partner Tutts. The execution and timing had to be precise given that we were going from a country town into the city of Newcastle for the export.

Enjoy

Pete
  • The Mill Shell leaving the site and heading to the holding bay outside of Cobar
  • At the foot of the Andes
  • Mill shell passing through a tunnel in Argentina heading to San Juan with our trucking partner Roman
  • The Mill Shell at the holding bay just outside of Cobar.
  • The Mill Shell coming into Cobar under police escort
  • The Mill Shell arrival in Newcastle Port.
  • Almost there
  • Lifting the 35 tonne Mill shell end on to transport heading to Newcastle. Mill Shell in the background
  • Train arriving in Cobar with our 21 x 40 Ft open Tops for all the smaller machinery parts and spares
  • Mill Shell and other cargo loaded into ships hold
  • Storage tanks loaded and heading to Newcastle
  • The vessel at Zarate Port in Argentina. discharge about to start